Estimate Your Notice to Owner and Claim of Lien Deadlines
Florida’s Construction Lien Law imposes strict deadlines on contractors, subcontractors, material suppliers, laborers, and other construction professionals seeking payment for work performed on real property.
Missing a required deadline may prevent an otherwise valid construction lien from being enforced. Use the Florida Construction Lien Deadline Calculator below to estimate two of the most important dates:
- The deadline to serve a Notice to Owner
- The deadline to record a Claim of Lien
Attorney Shaun Saliba has been concentrating his practice on Construction Law for over a decade. In 2024 alone, Shaun had a $363,000 judgment rendered at trial in a construction contract case.
Estimated Results
Your Florida Construction Lien Deadlines
Notice to Owner
Estimated 45-Day Deadline
Estimated from the first furnishing date entered above.
Claim of Lien
Estimated 90-Day Deadline
Estimated from the last furnishing date entered above.
!
Do not wait until these dates.
These results are estimates only. Service requirements,
final payment, contract termination, bonded-project rules,
clerk closures, and disputes about first or final furnishing
may create an earlier or different deadline.
Construction Lien Assistance
Have an Attorney Review Your Deadline
St. Johns Law Group assists contractors, subcontractors,
suppliers, developers, and property owners with Florida
construction lien and payment disputes.
Schedule a Consultation
Important disclaimer:
This calculator is provided for general educational purposes only and
is not legal advice. It does not create an attorney-client relationship.
It cannot determine whether you have lien rights, whether a Notice to
Owner is required, whether work qualifies as first or final furnishing,
or whether another deadline applies. Verify all deadlines with a
qualified Florida construction attorney.
Need Help Protecting Your Lien Rights?
Understanding Your Estimated Deadlines
Florida Notice to Owner Deadline
Many subcontractors, sub-subcontractors, material suppliers, and other lienors who do not have a direct contract with the property owner must serve a Notice to Owner before they can enforce a construction lien.
Under section 713.06, Florida Statutes, the Notice to Owner generally must be served:
- Before beginning to furnish labor, services, or materials; or
- No later than 45 days after first furnishing labor, services, or materials.
The notice must also be served before the owner makes final payment after receiving the contractor’s final payment affidavit. Failure to serve a required Notice to Owner on time can be a complete defense to enforcement of the lien.
Who May Need to Serve a Notice to Owner?
A Notice to Owner is commonly required from parties such as:
- Subcontractors
- Sub-subcontractors
- Material suppliers
- Suppliers to subcontractors
- Certain labor or service providers who lack a direct contract with the owner
Not every construction participant has the same notice requirements. For example, a contractor who contracts directly with the property owner is generally treated differently from a subcontractor or supplier who is not in privity with the owner.
The calculator should not be used to determine whether you are legally required to serve a Notice to Owner. That question should be evaluated separately.
Serving the Notice Is Different from Sending It
Florida law contains specific requirements for serving construction lien notices. The date a document is prepared, signed, placed in an envelope, or handed to a mailing service may not always be the legally controlling service date.
A Notice to Owner must also be directed to the required recipients identified by Florida law and the recorded Notice of Commencement. Depending on the project, copies may need to be served on the owner, contractor, subcontractor, lender, or another person designated to receive notices.
Because proof of timely service can become critical in a lien dispute, contractors and suppliers should maintain:
- A copy of the signed Notice to Owner
- Mailing and tracking documentation
- Delivery confirmations
- The recorded Notice of Commencement
- Contracts, invoices, delivery tickets, and daily work records
Florida Claim of Lien Deadline
A construction lien is not created merely by sending an invoice, demand letter, or Notice to Owner. A lienor must prepare and record a legally sufficient Claim of Lien in the public records of the county where the property is located.
Under section 713.08, Florida Statutes, a Claim of Lien generally may be recorded during the work or afterward, but no later than 90 days after the lienor’s final furnishing of labor, services, or materials.
The Claim of Lien must contain specific statutory information, including:
- The lienor’s name and address
- The person with whom the lienor contracted
- A description of the labor, services, or materials furnished
- A sufficient legal description of the property
- The property owner’s name
- The dates of first and final furnishing
- The unpaid amount
- Information concerning service of the Notice to Owner, when required
The Claim of Lien must be signed and sworn to or affirmed by the lienor or an authorized agent familiar with the facts.
What Is the “Final Furnishing” Date?
Determining the final furnishing date is one of the most frequently disputed issues in Florida construction lien cases.
The final furnishing date is not necessarily:
- The invoice date
- The date payment became due
- The date a payment request was rejected
- The date the contract was formally closed
- The date the contractor returned to inspect the property
- The date warranty work was performed
A return to the project for insignificant work, correction of defects, punch-list items, warranty service, or work performed merely to extend the lien deadline may not establish a new final furnishing date.
The calculator asks for the last date on which substantial contract labor, services, or materials were furnished. Because that determination is fact-specific, the calculated result should be reviewed by a Florida construction attorney.
Contract Termination Can Affect the Deadline
When the original construction contract is terminated under Florida’s Construction Lien Law, the deadline may be tied to the earlier of:
- Ninety days after termination; or
- Ninety days after the lienor’s final furnishing.
Accordingly, the ordinary 90-day calculation may not apply to every terminated or abandoned project.
Weekend and Holiday Deadline Rules
Florida law provides that when the last day of a Chapter 713 time period falls on a Saturday, Sunday, qualifying state holiday, clerk-observed holiday, or holiday designated by the chief judge, the period generally extends through the end of the next business day.
A deadline may also be tolled when the clerk’s office is closed because of an emergency and a document cannot be presented for recording or filing.
The calculator adjusts for Saturdays, Sundays, and commonly observed Florida state holidays. It cannot reliably identify:
- County-specific clerk holidays
- Holidays designated by a local chief judge
- Emergency courthouse closures
- Hurricane or disaster closures
- Temporary interruptions in electronic recording
- Changes in statutory holiday schedules
Do not rely on the calculator to wait until the final adjusted day.
Recording the Claim of Lien Is Not the Final Step
After recording, the Claim of Lien must generally be served on the owner. Failure to serve it before recording or within 15 days after recording may make the lien voidable to the extent a person entitled to rely on service was prejudiced by the delay.
A recorded construction lien also does not remain enforceable indefinitely. Unless shortened by another legal procedure, a Florida construction lien generally lasts for one year after recording unless an action to enforce the lien is commenced within that period.
An owner may substantially shorten that period by recording and serving a Notice of Contest of Lien. The lienor may then have only 60 days from service to file an enforcement lawsuit.
Other court procedures can shorten the enforcement period even further.
Common Florida Construction Lien Mistakes
Waiting Until Day 45 or Day 90
Mailing, service, recording, legal-description, notarization, and county-recording problems can occur. Construction participants should begin the lien process well before the estimated deadline.
Using the Wrong First-Furnishing Date
The date a contract was signed or a deposit was received is not necessarily the first date labor, services, or materials were furnished.
Using Punch-List or Warranty Work to Extend the Deadline
Minor corrective work may not restart the 90-day recording period.
Naming the Wrong Property Owner
The contracting party, project manager, tenant, developer, or general contractor may not be the record owner of the property.
Using an Incomplete Property Description
A street address alone may not always provide the legally sufficient description needed for a Claim of Lien.
Serving the Wrong People
The recorded Notice of Commencement may identify additional parties who must receive construction lien notices.
Calculating the Deadline but Ignoring the Service Deadline
Preparing a Notice to Owner or Claim of Lien does not necessarily mean it has been timely served or recorded.
Overstating the Lien Amount
Including amounts that are not lienable, or knowingly overstating a lien, can create serious legal problems and may expose the lienor to a fraudulent-lien claim.
Florida Construction Lien Representation
St. Johns Law Group represents contractors, subcontractors, suppliers, developers, property owners, businesses, and community associations in construction payment and lien matters.
Our construction attorneys can assist with:
Calculator Disclaimer
This Florida Construction Lien Deadline Calculator is provided for general educational and informational purposes only. It is not legal advice, does not create an attorney-client relationship, and should not be relied upon as a substitute for advice from a licensed Florida attorney.
The calculator makes simplified assumptions based solely on the dates entered by the user. It does not determine whether a person has construction lien rights, whether a Notice to Owner is required, whether a notice has been legally served, whether work constitutes first or final furnishing, whether work is substantial or merely corrective or warranty work, whether a contract has been terminated, whether the project is bonded, whether the property is public or private, or whether another statute or contractual deadline applies.
The calculator may not account for every federal, state, county, court, clerk, emergency, or locally observed holiday or closure. Users should independently verify all deadlines and should take action well before any calculated date.
Construction lien rights may be lost before the date displayed. Consult a qualified Florida construction attorney immediately regarding any actual or potential lien claim.
Florida’s Construction Lien Law is technical, deadline-driven, and strictly applied in many circumstances. An error involving the Notice to Owner, final furnishing date, property description, lien amount, service method, or recording deadline can impair important payment rights.
Contact St. Johns Law Group to discuss a construction lien, unpaid construction balance, Notice to Owner, Claim of Lien, lien foreclosure, or construction payment dispute.
Call: 📞 (904) 495-0400
Email: ✉️ info@sjlawgroup.com
Visit: 🌐 www.sjlawgroup.com